Owner/Client: Corps of Engineers New Orleans District
Year Complete: 2011
Scope of Work: Hydraulic Dredging
Project Cost: $66M
WMI’s Dredging Division was tasked with excavating 19 miles of maintenance material from the Calcasieu River.
Owner/Client: Corps of Engineers New Orleans District
Year Complete: 2011
Scope of Work: Hydraulic Dredging
Project Cost: $66M
WMI’s Dredging Division was tasked with excavating 19 miles of maintenance material from the Calcasieu River.
Owner/Client: USACE New Orleans District
Year Complete: Various
Scope of Work: Maintenance Dredging
Projects Cost: W912P8-11-C-0071: $12.M (current),W912P8-10-C-0117: $14 M (2011),W912P8-09-C-0103: $14 M (2010),W912P8-09-C-0086: $10 M (2009)
Over the years, Weeks Marine has performed numerous maintenance dredging projects on the Atchafalaya River system.
Owner/Client: USACE New Orleans District
Year Complete:2008
Scope of Work: Maintenance Dredging
Project Cost: W912P8-08-C-0034: $4.1 M, W912P8-08-C-0054: $4.7 M, W912P8-08-C-0072: $4.2 M, W912P8-08-C-0081: $5.2 M
Weeks Marine performed (4) four Mississippi River, Baton Rouge to the Gulf of Mexico, Southwest Pass to Cubits Gap, Hopper dredge rental contracts for the U.S. Army Corps of Engineers, New Orleans District in 2008.
Owner/Client: USACE Baltimore District
Year Complete: 2009
Scope of Work: Maintenance Dredging with Upland Disposal
Project Cost: $13.2M
WMI was contracted by the Corps of Engineers Baltimore District to dredge approximately 1.8M cubic yards of maintenance material from the Baltimore Harbor channels.
Owner/Client: USACE Jacksonville District
Year Complete: 2008
Scope of Work: Maintenance Dredging and Beach Renourishment.
Project Cost: $4.2M
The Kings Bay project was performed for the U.S. Army Corps of Engineers, Jacksonville District and was completed in 2008.